CHAPTER V - DOMESTIC WATER SUPPLY
DS
İ
Genel Müdürlü
ğ
ü
SİSTEMDE ÇALIŞACAK TÜNEL DELME MAKİNALARI
Tunnel Inlet
Tunnel Outlet
Construction
Shaft
Ventilation
Shaft
IŞIKLI
Regulator
ÇAMLIDERE
Dam
Plan of the Gerede Water Supply Project
Water Conveyance Tunnel Longitudinal Section
5.4.5.Water Supply Projects for TRNC-Turkish Republic of Northern Cyprus
There are two Water Supply Projects to
Turkish Republic of Northern Cyprus
(TRNC).
1. Kumköy-Serhatköy conveyance line
construction (In Operation).
2. Water Supply Project via pipe from Anamur
(Dragon) stream to TRNC (Ongoing).
1. Kumköy-Serhatköy Conveyance
Line
Kumköy-Serhatköy conveyance line begins from Kumköy water facilities located at the west part
of the TRNC. It extends to Gazimagosa located at the east part of the TRNC. It supplies
domestic water of two biggest settlements of TRNC, that is, Lefkoşa and Gazimogasa. It also
supplies domestic water of some villages on the route of the conveyance line. Presently,
Kumköy-Serhatköy main conveyance line is not enough to meet the demand of water. In order
to changed the existing line between Kumköy-Serhatköy with a new conveyance line, “
Kumköy
– Serhatköy Conveyance Line Construction”
work was on the agenda.
The work of Kumköy and Serhatköy conveyance line was put out the tender on 29
th
June 2006.
Pipeline conveyance line of 25 878 m in length, having ductile pipes Ø 800 mm in diameter as
well as a furcation to supply water to convey water to Middle East Technical University (METU)